Grantham Southern Relief Road July update - More overnight road closures planned as progress continues

By The Editor 6th Jul 2021

More overnight road closures are planned on the A1 Grantham by-pass as progress continues on the town's Southern Relief Road.

In an update for July, Lincolnshire County Council says earthworks, drainage and piling are underway for Phase Three.

Phase Three is the final part of the road between the A52 at Somerby Hill to the B1174 Old Great North Road.

In the update, Lincolnshire County Council states the following:

What we achieved in July and what we have planned for August.

What we achieved in June

Phase Two

Started out works to underside of new underpass

Began earthworks near the old underpass

Continued drainage and ducting works across the entire site

Commenced street lighting and signage installation across the entire site

Road surfacing, lining, ducting and drainage works to the A1

Removed central reservation on the A1

Phase Three Continue haul works / carry out drainage works / continue installation of piling platforms to the west side of site Installed track monitoring and instrumentation to measure pore water and railway movement to the east side of site Continued earthworks and set up a material processing yard on the east side of side Continued post-excavation archaeological reporting What's happening in July Phase Two Continue works to underside of new underpass Continue earthworks near the old underpass Continue drainage and ducting works / street lighting and signage installation across the entire site Continue central reservation drainage works on the A1 Begin safety fencing installation on the A1

Phase Three

Continue drainage works / build test pile platform / install test piles for Pier 2 of the new bridge on the west side of site

Process rocks on-site by crushing them to use a fill material on east side of site

Continue bulk earthworks and filling shoulders of site with core material on east side of site

Continue post-excavation archaeological reporting

Current/ongoing traffic restrictions and closures

50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton

On-going lane closures on the B1174 roundabout until the end of the scheme

Southbound A1 closure between Little Ponton and Harlaxton from Monday 5 July to Friday 9 July, 8pm to 6am

Upcoming traffic restrictions and closures Northbound lane closure from Monday 26 July to Friday 6 August, 8pm to 6am Northbound A1 closure between Little Ponton and Harlaxton from Monday 9 August to Friday 20 August, 8pm to 6am Southbound A1 closure between Little Ponton and Harlaxton from Monday 23 August to Friday 3 September, 8pm to 6am Northbound A1 closure between Little Ponton and Harlaxton from Monday 6 to Friday 24 September, 8pm to 6am Lincolnshire County Council says Phase 2 of the £102M 3.5km scheme is due for completion this autumn. This phase is between the A1 and the B1174. Phase 3 and the entire road Autumn 2021 is expected to be fully built/project complete in Winter 2023.

     

New grantham Jobs Section Launched!!
Vacancies updated hourly!!
Click here: grantham jobs

Share:


Sign-Up for our FREE Newsletter

We want to provide grantham with more and more clickbait-free local news.
To do that, we need a loyal newsletter following.
Help us survive and sign up to our FREE weekly newsletter.

Already subscribed? Thank you. Just press X or click here.
We won't pass your details on to anyone else.
By clicking the Subscribe button you agree to our Privacy Policy.