Work continues on Grantham Southern Relief Road
Works on the second phase of Grantham's new relief road are steadily progressing through the winter.
In a monthly update, Lincolnshire County Council has reported on what was achieved during November.
Continued drainage works to the western side of the scheme
Continued earthworks at the eastern side of the scheme
Recommenced piling works for second half of new A1 bridge
Installed temporary fencing and dug geotechnical trial holes for Phase Three
Continued post-excavation archaeological reporting
What's happening in December
Continue drainage works to the western side of the scheme
Continue earthworks across the entire site
Complete piling works / begin pile cropping and excavation works in preparation for concrete works for second half of new A1 bridge
Carry out planning works and site clearance for signage installation on A1
Continue Phase Three Anglian Water watermain diversion and BT ducting
Continue post-excavation archaeological reporting
Current/ongoing traffic restrictions and closures
50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton
The £102M 3.5km relief road is due for completion in Winter 2023.