Grantham Southern Relief Road update: Phase Three works now officially underway

By The Editor

5th May 2021 | Local News

Phase Three of the Grantham Southern Relief Road is underway.

Work on the final section of the £102M road began last month, as previously reported by Nub News.

The final phase of the relief road will link the A52 at Somerby Hill to the B1174, crossing the Witham Valley, River Witham and East Coast railway line with a new viaduct/bridge.

Work on the relief road's second phase, which will join the B1174 to the A1, is currently underway and expected to be complete later this year.

When opened, the whole Grantham Southern Relief Road will stretch for 3.5km, linking the A52 at Somerby Hill to the A1.

Lincolnshire County Council expects to have the entire relief road open by the end of 2023.

In its monthly progress report, the county council announced the following:

"Works for May include drainage and ducting across the entire site, installation of bridge foundations, and post evacuation archaeological reporting.

What was achieved in April:

Phase Two

Continued drainage works across the entire site

Started signage and street light installation

Began earthworks for the landscaped areas of site

Started construction of wingwalls for the new A1/B1174 connection

Carry out drainage and ducting works / install street lighting and signage / carry out surface water channel works on the A1

Phase Three Began stripping top soil across the entire site

Completed spring intercept drainage and continued outfall works

Continued haul road construction and B1174 ramp works

Completed site clearance of tree stumps and other remaining vegetation

Continued post-excavation archaeological reporting

What's happening in May

Phase Two

Continue drainage and ducting works across the entire site

Excavate under the new underpass

Close off and infill the existing underpass

Carry final bridge deck works and continue tying into the existing carriageway Phase Three Carry out drainage works to the west of the railway

Continue haul road construction on the west and east sides of site

Continue B1174 ramp works and piling platforms on the west side of site

Install haul bridge foundations / complete topsoil stripping / carry out bulk earthworks to the east side of site

Continue post-excavation archaeological reporting

Current/ongoing traffic restrictions and closures

50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton

On-going lane closures on the B1174 roundabout until the end of the scheme

Upcoming traffic restrictions and closures

Occasional off-peak lane restrictions on the B1174 roundabout, as needed"

The Grantham Southern Relief Road project is being led by Lincolnshire County Council and supported by South Kesteven District Council, Greater Lincolnshire LEP, Highways England, Department for Transport, Network Rail, Homes England and local businesses.

For the latest news on the Grantham Southern Relief Road, visit www.lincolnshire.gov.uk/majorprojects

     

New grantham Jobs Section Launched!!
Vacancies updated hourly!!
Click here: grantham jobs

Share:

Related Articles

Cocktail of the Week: Island Breeze. Image credit: Josh Tooley
Local Features

Cocktail of the Week: Island Breeze

Outside seating in the Coffee Room. Image credit: Easton Walled Gardens.
Local News

New Stationery and Book Shop opening at Easton Walled Gardens

Sign-Up for our FREE Newsletter

We want to provide grantham with more and more clickbait-free local news.
To do that, we need a loyal newsletter following.
Help us survive and sign up to our FREE weekly newsletter.

Already subscribed? Thank you. Just press X or click here.
We won't pass your details on to anyone else.
By clicking the Subscribe button you agree to our Privacy Policy.