Grantham Southern Relief Road update: Phase Three works now officially underway
By The Editor
5th May 2021 | Local News
Phase Three of the Grantham Southern Relief Road is underway.
Work on the final section of the £102M road began last month, as previously reported by Nub News.
The final phase of the relief road will link the A52 at Somerby Hill to the B1174, crossing the Witham Valley, River Witham and East Coast railway line with a new viaduct/bridge.
Work on the relief road's second phase, which will join the B1174 to the A1, is currently underway and expected to be complete later this year.
When opened, the whole Grantham Southern Relief Road will stretch for 3.5km, linking the A52 at Somerby Hill to the A1.
Lincolnshire County Council expects to have the entire relief road open by the end of 2023.
In its monthly progress report, the county council announced the following:
"Works for May include drainage and ducting across the entire site, installation of bridge foundations, and post evacuation archaeological reporting.
What was achieved in April:
Phase Two
Continued drainage works across the entire site
Started signage and street light installationBegan earthworks for the landscaped areas of site
Started construction of wingwalls for the new A1/B1174 connectionCarry out drainage and ducting works / install street lighting and signage / carry out surface water channel works on the A1
Phase Three Began stripping top soil across the entire siteCompleted spring intercept drainage and continued outfall works
Continued haul road construction and B1174 ramp worksCompleted site clearance of tree stumps and other remaining vegetation
Continued post-excavation archaeological reportingWhat's happening in May
Phase Two
Continue drainage and ducting works across the entire site
Excavate under the new underpassClose off and infill the existing underpass
Carry final bridge deck works and continue tying into the existing carriageway Phase Three Carry out drainage works to the west of the railwayContinue haul road construction on the west and east sides of site
Continue B1174 ramp works and piling platforms on the west side of siteInstall haul bridge foundations / complete topsoil stripping / carry out bulk earthworks to the east side of site
Continue post-excavation archaeological reportingCurrent/ongoing traffic restrictions and closures
50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little PontonOn-going lane closures on the B1174 roundabout until the end of the scheme
Upcoming traffic restrictions and closuresOccasional off-peak lane restrictions on the B1174 roundabout, as needed"
The Grantham Southern Relief Road project is being led by Lincolnshire County Council and supported by South Kesteven District Council, Greater Lincolnshire LEP, Highways England, Department for Transport, Network Rail, Homes England and local businesses.
For the latest news on the Grantham Southern Relief Road, visit www.lincolnshire.gov.uk/majorprojects