Grantham: Night time A1 closures to continue through August
By The Editor
6th Aug 2021 | Local News
Night time closures of the A1 Grantham by-pass are to continue through August as work progresses on the £102M Southern relief road.
During July Lincolnshire County Council contractors continued work to the underside of the new underpass, earthworks near the old underpass, drainage and ducting works, signage and street lighting.
In July, the contractors achieved:
Phase TwoContinued works to underside of new underpass
Continued earthworks near the old underpassContinued drainage and ducting works / street lighting and signage installation across the entire site
Completed central reservation drainage works and safety fencing on the A1Began ducting and street light installation on the A1
Phase Three
Continued digging out poor material and replacing with newInstalled test piles for Pier 2 of the new bridge
Installed sheet piles for haul road bridge on the west side of siteContinued bulk earthworks and filling shoulders of site with core material on east side of site
Continued filling embankment and processing crushed rocks on east side of siteContinue post-excavation archaeological reporting
This month;s work will include:
Phase Two
Continue works to underside of new underpassComplete earthworks near the old underpass
Continue drainage and ducting works / street lighting and signage installation across the entire siteBegin safety barrier and road surfacing across the entire site
Begin surfacing, water channel installation and verge works / continue ducting, signage and street light installation on the A1 Phase ThreeInstall below-ground embankment monitoring equipment / construct embankment / install new haul road bridge / begin installation of foundational concrete columns for new bridge on the west side of site
Continue bulk earthworks on east side of siteContinue post-excavation archaeological reporting
August will also see the current/ongoing traffic restrictions and closures
50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton
On-going lane closures on the B1174 roundabout until the end of the scheme
There will also be upcoming traffic restrictions and closures as follows:
Northbound A1 closure between Little Ponton and Harlaxton from Sunday 8 to Friday 13 August
Northbound A1 closure between Little Ponton and Harlaxton from Monday 16 to Friday 20 August
Southbound A1 closure between Little Ponton and Harlaxton from Monday 23 August to Friday 27, and Tuesday 31 August, 8pm to 6am
The 3.5km relief road is due to fully be open in Winter 2023. Phase, between the A1 and the roundabout on the B1174 should be complete this autumn.
For more information about this and other major highways projects, click on the link here.
New grantham Jobs Section Launched!!
Vacancies updated hourly!!
Click here: grantham jobs
Share: